Rathmines & Rathgar Roadworks

Reinstatement and resurfacing works are being carried out on the Rathmines Road and Richmond Street South between the junction at Military Road and junction with Harrington Street.

Similar works will take place on the Rathgar Road between the junction with Highfield Road and junction with Grosvenor Road.

These works commenced on the 19th August and will run for approximately 6 weeks; Sunday to Wednesday between the hours of 7.30pm each evening until 6am the following morning.

All road planning and mechanical breaking will be completed by 11pm each night but surfacing works will continue after this and there will be noise associated with this work.

Temporary traffic management plans will be put in place each evening and removed each morning and while access will be provided at all times there will be periods where short delays will occur.

The work is being carried out by SIAC Bituminous Products Ltd on behalf of Dublin City Council.

The National Transport Authority Funded Carriageway Renewal Works – Package 5a involves two sections of road as described above. In total, the works comprise  of 18,780m2  100mm depth of new surface and 1,447m2 reconstruction of damaged pavement (potholes etc..) The Works  also include for the reinstatement of road markings.